Marinwood Spends the Winter Rebuilding What It Uses All Summer

The Marinwood Pool is empty. Its water was pumped out the week of October 12. The next week a crew of six started jackhammering the old plaster loose and hauling it out by wheelbarrow, all day, for close to two weeks. If you walk past the fence at 775 Miller Creek Road now, you'll see bare shell where the blue used to be.

That pool is a good way into Marinwood this winter. The places neighbors use most in summer are the pool, the open-space fire roads and the corner at Marinwood Avenue. All three are being rebuilt or re-ruled this winter. Meanwhile the December events at the Community Center go on as usual, a few steps from the pool fence.

The Pool Is Down to Its Shell

The Marinwood Pool's season runs April through October, so the off-season is the one window when the pool can be taken apart without losing swim days. The district's November parks report says the plaster is fully removed. Crews are now shoring up weak spots in the gunite and setting new coping stones around the pool edge.

On October 30 the contractor, the architect and Marinwood staff met on site to review progress. The report says things "seem to be progressing according to plan and no major issues have arisen thus far." The November 10 board packet has photos of the drained pool and of the new coping going in.

The pool is the most visible project this winter. The rule change happening up on the hills behind it will probably matter more to more people.

The Park Rules Finally Mention E-Bikes

Marinwood's park rules are Ordinance 2011-03. They were rewritten in 2011, last amended in 2016, and say nothing about e-bikes. District Manager Eric Dreikosen's October staff report says e-bike ownership and use have "grown significantly" in the years since, along with e-bike use on district lands. Under the current wording, an e-bike falls under the ordinance's broad definition of "vehicle," which covers any wheeled conveyance, "motor powered" included.

The Park & Recreation Commission took up the issue on September 22. It recommended adding Class 1 e-bikes wherever ordinary bicycles are already allowed, and adding ADA mobility devices to the list of things that don't count as vehicles. The board held a public hearing on October 13. The amendment then went on the November 10 agenda for approval. The staff report recommends adoption and says the district received no further public comments. The district posts the final action at marinwood.org.

Here's how the proposed text changes the bicycle exception:

Ordinance 2011-03 Current text Proposed amendment
Who may ride Non-motorized bicycles Non-motorized bicycles or Class 1 e-bikes
Where Paved pathways, designated bike trails, open-space fire roads not signed against bikes Same
Speed 15 mph maximum, 5 mph when passing or on blind turns Same
"Vehicle" exemptions Baby carriages, strollers, district and emergency vehicles Adds ADA-applicable mobility devices

A Class 1 e-bike gives assistance only while the rider pedals, and the assist stops at 20 mph. Class 2 bikes can also run on a throttle. Class 3 bikes assist up to 28 mph. The staff report says allowing Class 1 is consistent with what similar agencies do. It also matches the county's own rules. Under AB 1778, the Marin e-bike safety pilot signed in September 2024, the county's e-bike laws page lists these:

  • Riders must be 16 or older to ride a Class 2 e-bike, and helmets are required at every age.
  • Class 1 and Class 2 e-bikes may use multi-use paved pathways maintained by the County of Marin.
  • All bicycles are limited to 15 mph on county-maintained pathways, and some paths are posted at 10 mph.
  • Class 3 e-bikes stay off bike paths and must use bike lanes, bike routes and roadways.

This is general information, not legal advice. If you're unsure what your bike is allowed to do on a given trail, check the posted signs and the district's current ordinance.

The same agenda has another trail item. Staff asked the board to extend the Oakview developer's road-and-bridge obligation from December 31, 2026 to April 30, 2027. The extra time lets the district hire a consultant to update the cost estimate for a planned multi-use trail. The consultant who did the original estimate has retired, and the developer agreed to the extension.

Across Miller Creek Road, Construction Keeps Its Own Hours

The third project is at the old Marinwood Plaza site on Marinwood Avenue. Four three-story buildings are going up there, along with a 1,040-square-foot retail space and a landscaped civic plaza open to the public from Marinwood Avenue. The county's project page, updated November 4, expects the homes to be ready in spring 2027, subject to construction progress.

The county says Marinwood Market will stay open during construction. The market's website lists hours of 7 a.m. to 7 p.m. The county's construction management plan calls for rebuilding the market's driveway and parking areas in phases so customers keep partial access while the new curbs and paving go in.

The county's June 2026 FAQ sets the construction hours:

  • Weekdays: 7 a.m. to 6 p.m. Crews and trucks may arrive at 7, but noise-producing work can't start before 8.
  • Saturdays: 9 a.m. to 5 p.m.
  • No construction: Sundays, Thanksgiving Day and Christmas Day.

Questions about construction go to Milestone Construction Group: Field Superintendent Kerry Eldredge at (916) 202-1381 or Project Manager Sriram Kora at (408) 677-6654. The FAQ also says the county is designing a separate Marinwood Avenue project. It would add a separated bike and pedestrian path, street lighting, landscaping, parking improvements and traffic calming, and take two to three months to build once it starts.

What Stays Put at 775 Miller Creek Road

With the pool shell, the fire roads and the Plaza corner all changing, the Community Center calendar runs on its usual December schedule. It's the one part of Marinwood's shared space this winter that looks the way it did a year ago. Recreation Director Luke Fretwell's welcome letter in the Fall/Winter 2026–2027 Marinwood Review is mostly about park cleanup after summer camps, and it blames some of the litter on "the infamous Marinwood wind." The winter calendar, in date order:

  1. November 23–24, Thanksgiving Break Camp. Ages 4 to 10, 9 a.m. to 3 p.m., $128 for residents and $152 for non-residents.
  2. November 27–28, Community Center closed for the Thanksgiving holiday.
  3. December 1–16, Letters to Santa. Kids can drop letters in the North Pole Mailbox on the Community Center's front patio from 9 a.m. December 1 through 5 p.m. December 16. Include a return address so Santa can write back.
  4. December 2, Las Gallinas Lions Club Holiday Party Dinner Meeting at the Community Center. Social hour starts at 5:30 p.m. and dinner at 6:30. The club calls itself Marinwood's only service club. It sponsors the Halloween pumpkin patch and the Easter Egg Hunt, and its February crab feed is next on its calendar.
  5. December 8 and 10, Holiday Art Workshops with Ms. Paula at Lucas Valley Elementary, 2:35 to 4:15 p.m., $72. Tuesday is for 1st through 3rd graders and Thursday for 2nd through 4th graders.
  6. December 11, Jingle Bell Jazz. The holiday concert runs 5 to 6:30 p.m. at the Community Center, with live music, a hot chocolate bar and photos with Santa. Admission is free, and the Santa photos have a small fee.
  7. December 16, Senior Stroll on the Marin Civic Center Lagoon Loop, about three-quarters of a mile. Meet at 110 Armory Way at 10 a.m.
  8. December 21–23 and 28–30, Winter Break Camp. Ages 3 through 6th grade, $194 per week for residents and $227 for non-residents.

American Mah Jongg open play continues Wednesdays at 1 p.m. for $2 a week, with no sessions on November 25, December 23 or December 30. The Community Center is also closed December 25. On Christmas Day the Community Center will be closed and the Plaza site quiet, because Christmas is also one of the construction no-work days. The pool's regular season starts again in April, and the county's current target for the Plaza homes is spring 2027.

If you're thinking about how changes like these affect your own street or your plans for spring, I'm happy to talk them through with you. Contact Pat Kelly to request a free home valuation or a market consultation, backed by local experience and Berkshire Hathaway HomeServices.